Query
Macho Creek BESS
Type
Entity Briefing
Entity
Macho Creek BESS
State
TN
Technology
battery
Generated
2026-10-19T19:02:34.461Z

Briefing on Macho Creek BESS

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
151 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2027-05-31
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Macho Creek BESS is a 151 MW Battery project in Texas, currently active.

Macho Creek BESS, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-05-31.

Queue ID
ERCOT-25INR0390
Location
Starr, Texas
Technology
Battery
Developer
Macho Creek BESS, LLC
Market / region
ERCOT
Point of interconnection
Tap 138kV 8793 RIO GRANDE CITY - 8806 LAS LOMAS

What stands out

1

Macho Creek BESS is a 151 MW Battery project in Texas with status active.

2

Macho Creek BESS, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-05-31.

Market and operating context

Queue date
2023-06-28
Proposed COD
2027-05-31
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Macho Creek BESS — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0390
LocationStarr, Texas
TechnologyBattery
DeveloperMacho Creek BESS, LLC
Market / regionERCOT
Point of interconnectionTap 138kV 8793 RIO GRANDE CITY - 8806 LAS LOMAS
Queue date2023-06-28
Proposed COD2027-05-31