Query
Knight Airport BESS I
Type
Entity Briefing
Entity
Knight Airport BESS I
State
TN
Technology
battery
Generated
2026-10-19T13:07:36.359Z

Briefing on Knight Airport BESS I

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
522 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2027-10-15
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Knight Airport BESS I is a 522 MW Battery project in Texas, currently active.

Airport Storage I LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-10-15.

Queue ID
ERCOT-26INR0545
Location
Harris, Texas
Technology
Battery
Developer
Airport Storage I LLC
Market / region
ERCOT
Point of interconnection
Tap 138kV 48126 Gulfgate - 48199 Knight 06 and 42680 Garden Villas - 42770 Ashville 06

What stands out

1

Knight Airport BESS I is a 522 MW Battery project in Texas with status active.

2

Airport Storage I LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-10-15.

Market and operating context

Queue date
2024-08-16
Proposed COD
2027-10-15
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Knight Airport BESS I — verified asset snapshot

FieldValue
Queue IDERCOT-26INR0545
LocationHarris, Texas
TechnologyBattery
DeveloperAirport Storage I LLC
Market / regionERCOT
Point of interconnectionTap 138kV 48126 Gulfgate - 48199 Knight 06 and 42680 Garden Villas - 42770 Ashville 06
Queue date2024-08-16
Proposed COD2027-10-15