Knight Airport BESS I
522.46 MW storage in Harris, TX · In queue since August 2024 · Proposed COD October 2027
522.46 MW
Capacity
1
Components
Battery
2y 3m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-15
Projected COD moved
1 time
Jul 2026 → Oct 2027
Net change
+15 months
first report to latest
Capacity
522 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0545/knight-airport-bess-i
- interconnection.fyi/project/ercot-26inr0545
- ercotqueue.com/project/26INR0545
- ercotqueue.com/developer/airport-storage-i-llc
Commercial operation date: No news or press-release sources give a COD. Cleanview says 'Expected online 2027', which matches the LBNL proposed COD of 2027-10-15 but looks derived from the same queue data. ercotqueue.com lists the project as 'No IA' with a 1% build-chance, so the date is unlikely to be firm.
Developer: Only the LBNL filing entity and ercotqueue.com, which repeats the same name, identify a developer. No parent or operating company was found in any source, so the shell LLC cannot be resolved to a sponsor.
Status: LBNL, interconnection.fyi and ercotqueue.com all show the project as active in the queue. No source reports construction, withdrawal or suspension.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Knight Airport BESS I project is a proposed 522.46 MW battery storage project located in Harris County, Texas. The developer is Airport Storage I LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0545, with a queue entry date of August 16, 2024, and a proposed commercial operation date of October 15, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is Tap 138kV 48126 Gulfgate - 48199 Knight 06 and 42680 Garden Villas - 42770 Ashville 06.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Harris
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Airport Storage I LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 48126 Gulfgate - 48199 Knight 06 and 42680 Garden Villas - 42770 Ashville 06
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- POI Substation
- Gulfgate Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.