Query
Knickerbocker Storage
Type
Entity Briefing
Entity
Knickerbocker Storage
Generated
2026-10-19T19:00:31.181Z

Briefing on Knickerbocker Storage

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
25 MW
Proposed capacity
suspended
Current status
Other
Technology
ERCOT
Market / region
2028-06-01
Proposed COD
Facility Study
Queue phase
Briefing/projectsuspended

Knickerbocker Storage is a 25 MW Other project in Texas, currently suspended.

Knickerbocker Solar LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-06-01.

Queue ID
ERCOT-21INR0446
Location
Tom Green, Texas
Technology
Other
Developer
Knickerbocker Solar LLC
Market / region
ERCOT
Point of interconnection
Tap 345kV 76003 Big Hill - 76009 Twin Buttes

What stands out

1

Knickerbocker Storage is a 25 MW Other project in Texas with status suspended.

2

Knickerbocker Solar LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-06-01.

Market and operating context

Queue date
2019-12-18
Proposed COD
2028-06-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Knickerbocker Storage — verified asset snapshot

FieldValue
Queue IDERCOT-21INR0446
LocationTom Green, Texas
TechnologyOther
DeveloperKnickerbocker Solar LLC
Market / regionERCOT
Point of interconnectionTap 345kV 76003 Big Hill - 76009 Twin Buttes
Queue date2019-12-18
Proposed COD2028-06-01