Briefing/projectactive
KAWICH is a 700 MW Solar+Battery project in Nevada, currently active.
The reported queue phase is C14. Proposed COD is 2029-07-27.
- Queue ID
- CAISO-2147
- Location
- Clark, Nevada
- Technology
- Solar+Battery
- Market / region
- CAISO
- Point of interconnection
- Innovation-Desert View 230 kV Line
What stands out
1
KAWICH is a 700 MW Solar+Battery project in Nevada with status active.
2
The reported queue phase is C14; proposed COD is 2029-07-27.
Market and operating context
- Queue date
- 2021-04-15
- Proposed COD
- 2029-07-27
- IA status
- IA Executed
- Study phase
- C14
- Service type
- NRIS
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.