Briefing/projectactive
Juno 3 Solar is a 500 MW Solar project in Texas, currently active.
Juno Solar 3 is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-11-30.
- Queue ID
- ERCOT-26INR0621
- Location
- Borden, Texas
- Technology
- Solar
- Developer
- Juno Solar 3
- Market / region
- ERCOT
- Point of interconnection
- #59916 Buck Canyon 345kV
What stands out
1
Juno 3 Solar is a 500 MW Solar project in Texas with status active.
2
Juno Solar 3 is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2027-11-30.
4
Latest linked story: “SB Energy inaugurates 900MW Texas PV cluster with Google data centre PPA” (PV Tech, 2024-10-21).
Market and operating context
- Queue date
- 2025-03-24
- Proposed COD
- 2027-11-30
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters