Briefing on HyFuels Green Lake Solar

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
347 MW
Proposed capacity
active
Current status
Solar
Technology
ERCOT
Market / region
2027-12-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

HyFuels Green Lake Solar is a 347 MW Solar project in Texas, currently active.

HyFuels Green Lake Solar LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-12-01.

Queue ID
ERCOT-26INR0019
Location
Victoria, Texas
Technology
Solar
Developer
HyFuels Green Lake Solar LLC
Market / region
ERCOT
Point of interconnection
Dokmai 138kV Substation (bus #80090)

What stands out

1

HyFuels Green Lake Solar is a 347 MW Solar project in Texas with status active.

2

HyFuels Green Lake Solar LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-12-01.

Market and operating context

Queue date
2022-09-27
Proposed COD
2027-12-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

HyFuels Green Lake Solar — verified asset snapshot

FieldValue
Queue IDERCOT-26INR0019
LocationVictoria, Texas
TechnologySolar
DeveloperHyFuels Green Lake Solar LLC
Market / regionERCOT
Point of interconnectionDokmai 138kV Substation (bus #80090)
Queue date2022-09-27
Proposed COD2027-12-01