Query
Holtsville 138kV Energy Storage
Type
Entity Briefing
Entity
Holtsville 138kV Energy Storage
Technology
battery
Generated
2026-10-10T20:08:02.390Z

Briefing on Holtsville 138kV Energy Storage

Entity Briefing
Generated Oct 10, 2026·Dataset freshness not reported
110 MW
Proposed capacity
active
Current status
Battery
Technology
NYISO
Market / region
2026-09-01
Proposed COD
System Impact Study
Queue phase
Briefing/projectactive

Holtsville 138kV Energy Storage is a 110 MW Battery project in New York, currently active.

Holtsville Energy Storage, LLC is the reported developer. The reported queue phase is System Impact Study. Proposed COD is 2026-09-01.

Queue ID
NYISO-956
Location
Suffolk, New York
Technology
Battery
Developer
Holtsville Energy Storage, LLC
Market / region
NYISO
Point of interconnection
West Bus 138 kV

What stands out

1

Holtsville 138kV Energy Storage is a 110 MW Battery project in New York with status active.

2

Holtsville Energy Storage, LLC is the reported developer.

3

The reported queue phase is System Impact Study; proposed COD is 2026-09-01.

4

Latest linked story: “Energy company files lawsuit over building Holtsville battery energy storage system” (News12 | Long Island, 2026-01-09).

Market and operating context

Queue date
2019-12-10
Proposed COD
2026-09-01
IA status
System Impact Study
Study phase
System Impact Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Holtsville 138kV Energy Storage — verified asset snapshot

FieldValue
Queue IDNYISO-956
LocationSuffolk, New York
TechnologyBattery
DeveloperHoltsville Energy Storage, LLC
Market / regionNYISO
Point of interconnectionWest Bus 138 kV
Queue date2019-12-10
Proposed COD2026-09-01