Query
Holstein 2 Energy Storage
Type
Entity Briefing
Entity
Holstein 2 Energy Storage
Technology
battery
Generated
2026-10-19T09:02:00.225Z

Briefing on Holstein 2 Energy Storage

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
102 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2027-05-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Holstein 2 Energy Storage is a 102 MW Solar+Battery project in Texas, currently active.

229HD 8me LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-05-01.

Queue ID
ERCOT-21INR0430
Location
Nolan, Texas
Technology
Solar+Battery
Developer
229HD 8me LLC
Market / region
ERCOT
Point of interconnection
11406 Central Bluff 345kV

What stands out

1

Holstein 2 Energy Storage is a 102 MW Solar+Battery project in Texas with status active.

2

229HD 8me LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-05-01.

4

Latest linked story: “New Texas law threatens viability of battery energy storage systems” (Trellis Group, 2025-06-12).

Market and operating context

Queue date
2019-08-26
Proposed COD
2027-05-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Holstein 2 Energy Storage — verified asset snapshot

FieldValue
Queue IDERCOT-21INR0430
LocationNolan, Texas
TechnologySolar+Battery
Developer229HD 8me LLC
Market / regionERCOT
Point of interconnection11406 Central Bluff 345kV
Queue date2019-08-26
Proposed COD2027-05-01