Briefing/projectactive
Hobby BESS I is a 603 MW Battery project in Texas, currently active.
Airport Storage II LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-10-15.
- Queue ID
- ERCOT-26INR0546
- Location
- Harris, Texas
- Technology
- Battery
- Developer
- Airport Storage II LLC
- Market / region
- ERCOT
- Point of interconnection
- Double Tap 138kV 42680 Garden Villas – 48250 Hall & 42680 Garden Villas – 48013 Chocolate Bayou
What stands out
1
Hobby BESS I is a 603 MW Battery project in Texas with status active.
2
Airport Storage II LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2027-10-15.
Market and operating context
- Queue date
- 2024-09-04
- Proposed COD
- 2027-10-15
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.