Headcamp Energy Storage Plant is a 153 MW Battery project in Texas, currently active.
Momentum Headcamp LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-04-30.
- Queue ID
- ERCOT-23INR0401
- Location
- Pecos, Texas
- Technology
- Battery
- Developer
- Momentum Headcamp LLC
- Market / region
- ERCOT
- Point of interconnection
- tap 138kV 38331 TN Alamo St – 38455 TN Holiday
What stands out
Headcamp Energy Storage Plant is a 153 MW Battery project in Texas with status active.
Momentum Headcamp LLC is the reported developer.
The reported queue phase is IA Executed; proposed COD is 2026-04-30.
Latest linked story: “Lydian Energy Secures $233M in Project Financing to Advance Battery Storage Projects Across Texas” (Yahoo Finance, 2025-07-09).
Market and operating context
- Queue date
- 2021-12-03
- Proposed COD
- 2026-04-30
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.