Query
Headcamp Energy Storage Plant
Type
Entity Briefing
Entity
Headcamp Energy Storage Plant
Technology
battery
Generated
2026-10-19T17:29:26.050Z

Briefing on Headcamp Energy Storage Plant

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
153 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2026-04-30
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Headcamp Energy Storage Plant is a 153 MW Battery project in Texas, currently active.

Momentum Headcamp LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-04-30.

Queue ID
ERCOT-23INR0401
Location
Pecos, Texas
Technology
Battery
Developer
Momentum Headcamp LLC
Market / region
ERCOT
Point of interconnection
tap 138kV 38331 TN Alamo St – 38455 TN Holiday

What stands out

1

Headcamp Energy Storage Plant is a 153 MW Battery project in Texas with status active.

2

Momentum Headcamp LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2026-04-30.

4

Latest linked story: “Lydian Energy Secures $233M in Project Financing to Advance Battery Storage Projects Across Texas” (Yahoo Finance, 2025-07-09).

Market and operating context

Queue date
2021-12-03
Proposed COD
2026-04-30
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Headcamp Energy Storage Plant — verified asset snapshot

FieldValue
Queue IDERCOT-23INR0401
LocationPecos, Texas
TechnologyBattery
DeveloperMomentum Headcamp LLC
Market / regionERCOT
Point of interconnectiontap 138kV 38331 TN Alamo St – 38455 TN Holiday
Queue date2021-12-03
Proposed COD2026-04-30