Briefing on Harryoung Solar

Entity Briefing
Generated Oct 20, 2026·Dataset freshness not reported
190 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2028-05-15
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Harryoung Solar is a 190 MW Solar+Battery project in Texas, currently active.

Gransolar Group (GRS) is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-05-15.

Queue ID
ERCOT-25INR0270
Location
Cameron, Texas
Technology
Solar+Battery
Developer
Gransolar Group (GRS)
Market / region
ERCOT
Point of interconnection
Tap 8319 Rio Hondo - SOUTH SANTA ROSA: 8359, 138kV

What stands out

1

Harryoung Solar is a 190 MW Solar+Battery project in Texas with status active.

2

Gransolar Group (GRS) is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-05-15.

Market and operating context

Queue date
2022-11-23
Proposed COD
2028-05-15
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Harryoung Solar — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0270
LocationCameron, Texas
TechnologySolar+Battery
DeveloperGransolar Group (GRS)
Market / regionERCOT
Point of interconnectionTap 8319 Rio Hondo - SOUTH SANTA ROSA: 8359, 138kV
Queue date2022-11-23
Proposed COD2028-05-15