Briefing/projectactive
Grover Hill Wind Project is a 140 MW Wind project in Ohio, currently active.
The reported queue phase is IA Executed. Proposed COD is 2026-02-05.
- Queue ID
- PJM-AE1-245
- Location
- Paulding, Ohio
- Technology
- Wind
- Market / region
- PJM
- Point of interconnection
- Haviland 138 kV
What stands out
1
Grover Hill Wind Project is a 140 MW Wind project in Ohio with status active.
2
The reported queue phase is IA Executed; proposed COD is 2026-02-05.
3
Latest linked story: “Siting board approves transmission line for future Grover Hill Wind Farm in Paulding County” (Toledo Blade, 2023-03-17).
Market and operating context
- Queue date
- 2018-09-18
- Proposed COD
- 2026-02-05
- IA status
- IA Executed
- Study phase
- IA Executed
- Service type
- NRIS
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.