Greyhound Solar - Phase F
Type
Entity Briefing
Entity
Greyhound Solar - Phase F
Generated
2026-10-19T15:59:06.520Z

Briefing on Greyhound Solar - Phase F

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
102 MW
Proposed capacity
active
Current status
Solar
Technology
ERCOT
Market / region
2025-11-13
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Greyhound Solar - Phase F is a 102 MW Solar project in Texas, currently active.

ROCKHOUND SOLAR 2 LLC DBA GREYHOUND SOLAR is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2025-11-13.

Queue ID
ERCOT-26INR0670
Location
Ector, Texas
Technology
Solar
Developer
ROCKHOUND SOLAR 2 LLC DBA GREYHOUND SOLAR
Market / region
ERCOT
Point of interconnection
Tap 345kV 11010 Wolf - 1018 Moss

What stands out

1

Greyhound Solar - Phase F is a 102 MW Solar project in Texas with status active.

2

ROCKHOUND SOLAR 2 LLC DBA GREYHOUND SOLAR is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2025-11-13.

Market and operating context

Queue date
2025-04-17
Proposed COD
2025-11-13
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Greyhound Solar - Phase F — verified asset snapshot

FieldValue
Queue IDERCOT-26INR0670
LocationEctor, Texas
TechnologySolar
DeveloperROCKHOUND SOLAR 2 LLC DBA GREYHOUND SOLAR
Market / regionERCOT
Point of interconnectionTap 345kV 11010 Wolf - 1018 Moss
Queue date2025-04-17
Proposed COD2025-11-13