Query
Great Rock BESS
Type
Entity Briefing
Entity
Great Rock BESS
State
TN
Technology
battery
Generated
2026-10-19T18:07:57.619Z

Briefing on Great Rock BESS

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
301 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2027-12-20
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Great Rock BESS is a 301 MW Battery project in Texas, currently active.

Black Mountain Energy Storage II is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-12-20.

Queue ID
ERCOT-25INR0230
Location
Leon, Texas
Technology
Battery
Developer
Black Mountain Energy Storage II
Market / region
ERCOT
Point of interconnection
Tap 345kV 46020 Limestone - 967 Gibbon Creek Ckt 18

What stands out

1

Great Rock BESS is a 301 MW Battery project in Texas with status active.

2

Black Mountain Energy Storage II is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2027-12-20.

Market and operating context

Queue date
2022-11-07
Proposed COD
2027-12-20
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Great Rock BESS — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0230
LocationLeon, Texas
TechnologyBattery
DeveloperBlack Mountain Energy Storage II
Market / regionERCOT
Point of interconnectionTap 345kV 46020 Limestone - 967 Gibbon Creek Ckt 18
Queue date2022-11-07
Proposed COD2027-12-20