Great Rock BESS
300.9 MW storage in Leon, TX · In queue since November 2022 · Proposed COD December 2027
300.9 MW
Capacity
1
Components
Battery
4 years
In Queue
IA Executed
IA Phase
Signed Aug 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 9m
IA → COD
3y 4m
Total Duration
1y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2027-12-20
Projected COD moved
7 times
May 2025 → Dec 2027
Net change
+31 months
first report to latest
Capacity
307 → 301 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Generation Interconnection Agreement between CTT and Black Mountain Energy Storage II for Great Rock BESS (IA date from LBNL; agreement filed in PUC Docket 35077).
interchange.puc.texas.govResearch sources and reasoning (6 recorded sources)
low confidence at research time
- interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=1935
- interconnection.fyi/project/ercot-25inr0230
- cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0230/great-rock-bess
- ercotqueue.com/project/25INR0230
- energy-storage.news/esvolta-acquires-300mwh-ercot-bess-from-black-mountain-energy-storage/
- crglc.org/projects/
Commercial operation date: Only the LBNL/ERCOT queue date (2027-12-20) is available. Cleanview's "Expected online 2027" and interconnection.fyi's December 2027 date appear to be mirrored from the queue, so they are not independent confirmation, and no developer press release gives a different target.
Developer: A PUC Texas filing confirms the GIA between CTT and Black Mountain Energy Storage II for Great Rock BESS. Aggregators list the project owner as Great Rock Storage LLC, and trade press names Black Mountain Energy Storage (BMES) as the operating developer. The parent link is inferred from naming, not stated explicitly for this project.
Status: LBNL shows the project active with an IA executed, and the GIA appears in the PUC Texas docket. Aggregator claims of 'Construction' (ercotqueue.com) and 'operational' (interxdata) conflict with each other and are unverified, so I did not adopt them.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Great Rock BESS project is a proposed 300.9 MW battery storage project located in Leon County, Texas. The developer is Black Mountain Energy Storage II. It is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0230, with a queue entry date of November 7, 2022, and a proposed commercial operation date of December 20, 2027.
The project's interconnection agreement was executed on August 23, 2024. The point of interconnection is Tap 345kV 46020 Limestone - 967 Gibbon Creek Ckt 18.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Leon
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Black Mountain Energy Storage II
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 46020 Limestone - 967 Gibbon Creek Ckt 18
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LEG_LEG_G1
- POI Substation
- Limestone Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.