Briefing on Grapevine 1

Entity Briefing
Generated Oct 6, 2026·Dataset freshness not reported
205 MW
Proposed capacity
active
Current status
Solar
Technology
CAISO
Market / region
2031-06-01
Proposed COD
Cluster 15
Queue phase
Briefing/projectactive

Grapevine 1 is a 205 MW Solar project in Nevada, currently active.

The reported queue phase is Cluster 15. Proposed COD is 2031-06-01.

Queue ID
CAISO-2238
Location
Nye, Nevada
Technology
Solar
Market / region
CAISO
Point of interconnection
VALLEY SWITCH 230 kV

What stands out

1

Grapevine 1 is a 205 MW Solar project in Nevada with status active.

2

The reported queue phase is Cluster 15; proposed COD is 2031-06-01.

Market and operating context

Queue date
2023-04-17
Proposed COD
2031-06-01
IA status
Not Started
Study phase
Cluster 15
Service type
ERIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Grapevine 1 — verified asset snapshot

FieldValue
Queue IDCAISO-2238
LocationNye, Nevada
TechnologySolar
Market / regionCAISO
Point of interconnectionVALLEY SWITCH 230 kV
Queue date2023-04-17
Proposed COD2031-06-01
IA statusNot Started