Grapevine 1 (CAISO-2238) — Project Summary

Queue ID
CAISO-2238
Capacity
204.58 MW
Technology
Solar
Status
active
Location
Nye, NV
Region
CAISO
Developer
—
IA Status
Not Started

Grapevine 1

CAISO-2238BetaActiveSolarCAISOLBNL

204.58 MW generation in Nye, NV · In queue since April 2023 · Proposed COD June 2031

BA: NEVPISO/RTO: CAISONERC: WECCRC: SPPW

204.58 MW

Capacity

1

Components

Solar

3y 7m

In Queue

Not Started

IA Phase

COD target: 2031

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

8y 2m

Study Phase

Cluster 15

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2031-06-01

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Jun 2031
From queue filing
Developer in saved assessment
—
Status at research time
Active
Active — early-stage queue position (Cluster 15, IA Not Started), no construction or financing signals
Financing
Not recorded

Milestones in this assessment

IA executedApr 17, 2023Latest in this assessment

Queue application submitted to CAISO Cluster 15

caiso.com
Research sources and reasoning (4 recorded sources)

low confidence at research time

  1. cleanview.co/power-projects/planned/solar-farms/nevada/54945_photovoltaic/grapevine-1
  2. renewablesinfo.org/project/caiso-54945-grapevine-1
  3. caiso.com/documents/cluster-15-interconnection-requests.xlsx
  4. interconnection.fyi/project/caiso-54945

Commercial operation date: LBNL queue filing shows June 2031 COD. Cleanview aggregator sites echo this date (May/June 2031 variants). No developer press releases or financing announcements found to contradict or update this target.

Developer: LBNL filing shows null developer. Renewablesinfo.org mentions 'GLW' as developer but provides no context or verification. No press releases, corporate announcements, or credible news sources identify the project sponsor.

Status: LBNL status is 'active' with IA Not Started. No news of permitting, financing, groundbreaking, or developer activity found. Project appears to be in initial interconnection study phase.

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Grapevine 1 is a proposed solar generation project located in Nye County, Nevada, with a planned capacity of 204.58 MW. The project is listed in the interconnection queue of the California Independent System Operator (CAISO) under queue ID CAISO-2238, with GLW identified as the interconnecting utility. It is designed to connect to the grid at the Valley Switch 230 kV substation and has requested Energy Resource Interconnection Service (ERIS).

The project entered the CAISO queue on April 17, 2023, and is being evaluated as part of the Cluster 15 study process. Its status in the queue is active, and its proposed commercial operation date is June 1, 2031. As of the latest available data, the interconnection agreement process has not started.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

NV

County

Nye

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

—

Utility

GLW

Entity

CAISO

Service Type

ERIS

Point of Interconnection

VALLEY SWITCH 230 kV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_NP15_GEN-APND
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.