Briefing/projectactive
GAMAY ENERGY STORAGE is a 419 MW Battery project in Texas, currently active.
GAMAY ENERGY STORAGE LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2028-01-01.
- Queue ID
- ERCOT-26INR0417
- Location
- Brazoria, Texas
- Technology
- Battery
- Developer
- GAMAY ENERGY STORAGE LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 138 kV Line from TNFM524 (39703) to West Columbia Main (39500), in Brazoria County.
What stands out
1
GAMAY ENERGY STORAGE is a 419 MW Battery project in Texas with status active.
2
GAMAY ENERGY STORAGE LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2028-01-01.
Market and operating context
- Queue date
- 2024-02-07
- Proposed COD
- 2028-01-01
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.