Frye Storage is a 504 MW Solar+Battery project in Texas, currently active.
Hecate Energy Frye Storage LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-12-01.
- Queue ID
- ERCOT-22INR0402
- Location
- Swisher, Texas
- Technology
- Solar+Battery
- Developer
- Hecate Energy Frye Storage LLC
- Market / region
- ERCOT
- Point of interconnection
- new 345kV sub Kress connecting both 23912 Ogallala - 23914 Tule Canyon circuits
What stands out
Frye Storage is a 504 MW Solar+Battery project in Texas with status active.
Hecate Energy Frye Storage LLC is the reported developer.
The reported queue phase is Facility Study; proposed COD is 2028-12-01.
Latest linked story: “Stonepeak acquires stake in Repsol’s 777MW US solar-plus-storage portfolio” (PV Tech, 2025-04-30).
Market and operating context
- Queue date
- 2020-09-02
- Proposed COD
- 2028-12-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters