Briefing/projectactive
FRIENDSWOOD ENERGY GENCO is a 144 MW Gas project in Texas, currently active.
Shell is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-05-08.
- Queue ID
- ERCOT-24INR0456
- Location
- Harris, Texas
- Technology
- Gas
- Developer
- Shell
- Market / region
- ERCOT
- Point of interconnection
- 47170 H O CLARKE 138KV
What stands out
1
FRIENDSWOOD ENERGY GENCO is a 144 MW Gas project in Texas with status active.
2
Shell is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2026-05-08.
4
Latest linked story: “Houston power plant to enter service this summer” (The Business Journals, 2017-01-25).
Market and operating context
- Queue date
- 2022-12-07
- Proposed COD
- 2026-05-08
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.