Query
Enfinity Post Oak Storage SLF in ISO New England queue pipeline — 1 projects by technology and status
Type
Entity Briefing
Entity
Enfinity Post Oak Storage SLF
ISO/RTO
isone
Technology
battery
Generated
2026-10-13T19:54:24.676Z

Briefing on Enfinity Post Oak Storage SLF

Entity Briefing
Generated Oct 13, 2026·Dataset freshness not reported
active
Current status
Battery
Technology
ERCOT
Market / region
2029-12-18
Proposed COD
Briefing/projectactive

Enfinity Post Oak Storage SLF is a 0 MW Battery project in Texas, currently active.

EG White Oak LLC is the reported developer. Proposed COD is 2029-12-18.

Queue ID
ERCOT-29INR0292
Location
Borden, Texas
Technology
Battery
Developer
EG White Oak LLC
Market / region
ERCOT
Point of interconnection
345kV Long Draw (59900) to Sand Bluff (59902) Transmission line

What stands out

1

Enfinity Post Oak Storage SLF is a 0 MW Battery project in Texas with status active.

2

EG White Oak LLC is the reported developer.

3

proposed COD is 2029-12-18.

Market and operating context

Queue date
2026-03-30
Proposed COD
2029-12-18

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Enfinity Post Oak Storage SLF — verified asset snapshot

FieldValue
Queue IDERCOT-29INR0292
LocationBorden, Texas
TechnologyBattery
DeveloperEG White Oak LLC
Market / regionERCOT
Point of interconnection345kV Long Draw (59900) to Sand Bluff (59902) Transmission line
Queue date2026-03-30
Proposed COD2029-12-18