Elevate Arthur Kill II is a 180 MW Battery project in New York, currently active.
Lighthouse Arthur Kill II, LLC is the reported developer. The reported queue phase is C24. Proposed COD is 2028-06-01.
- Queue ID
- NYISO-C24-131
- Location
- Richmond, New York
- Technology
- Battery
- Developer
- Lighthouse Arthur Kill II, LLC
- Market / region
- NYISO
- Point of interconnection
- Fresh Kills 345 kV substation
What stands out
Elevate Arthur Kill II is a 180 MW Battery project in New York with status active.
Lighthouse Arthur Kill II, LLC is the reported developer.
The reported queue phase is C24; proposed COD is 2028-06-01.
Latest linked story: “Duke invests $100M in batteries in Belmont; could raise that to $1 billion for Gaston County” (Business North Carolina, 2026-01-14).
Market and operating context
- Queue date
- 2024-09-05
- Proposed COD
- 2028-06-01
- Study phase
- C24
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.