Elevate Arthur Kill II
180 MW storage in Richmond, NY · In queue since September 2024 · Proposed COD June 2028
180 MW
Capacity
1
Components
Battery
1y 10m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 9m
Study Phase
C24
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
Entered NYISO interconnection queue as C24-131
The Elevate Arthur Kill II project is a proposed 180 MW battery storage project located in Richmond County, New York. The developer is Elevate Arthur Kill II, LLC, and the proposed point of interconnection is the Fresh Kills 345 kV substation. The project is currently active in the NYISO interconnection queue (queue ID NYISO-C24-131), with a queue entry date of September 5, 2024, and a proposed commercial operation date of June 1, 2027.
The Elevate Arthur Kill II project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Richmond
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Lighthouse Arthur Kill II, LLC
Utility
ConEd
Entity
NYISO
Service Type
—
Point of Interconnection
Fresh Kills 345 kV substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE J
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ARTHUR_KILL_2
- POI Substation
- Fresh Kills Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26