Dry Bridge Storage is a 20 MW Batteries asset in PJM Interconnection, currently Operating.
Dry Bridge Storage is reported in Virginia since 2023 under Dominion Energy. Available operating and financial measures include -2.0% capacity factor and -4 GWh annual generation; $1361/kW reported CapEx.
- Location
- Chesterfield, Virginia
- Technology
- Batteries
- Owner / parent
- Dominion Energy
- Operator
- Dominion Energy Inc.
- Grid
- PJM Interconnection
- Plant ID
- 65044
What stands out
Dry Bridge Storage is a 20 MW Batteries asset in Virginia with status Operating.
Latest annual operating measures report -2.0% capacity factor and -4 GWh annual generation.
Available financial measures include $1361/kW CapEx.
Latest linked story: “Could IW ban battery storage? At least one Virginia county has.” (Smithfield Times, 2026-02-28).
Market and operating context
- ISO / market
- PJM Interconnection
- Balancing authority
- PJM Interconnection, LLC
- NERC region
- SERC
- State rank
- #3 of 6
- National rank
- #531 of 994
Why it matters
For this asset in PJM Interconnection, operating status, generation, ownership, and linked events are the primary facts for performance and asset-level diligence. The exact chart and source-linked records below let the reader test those facts before moving to a deeper report.