Briefing on DARDEN

Entity Briefing
Generated Oct 13, 2026·Dataset freshness not reported
2.4 GW
Proposed capacity
active
Current status
Solar+Battery
Technology
CAISO
Market / region
2027-07-19
Proposed COD
C14
Queue phase
Briefing/projectactive

DARDEN is a 2.4 GW Solar+Battery project in California, currently active.

The reported queue phase is C14. Proposed COD is 2027-07-19.

Queue ID
CAISO-1949
Location
Fresno, California
Technology
Solar+Battery
Market / region
CAISO
Point of interconnection
Manning-Midway 500kV Line

What stands out

1

DARDEN is a 2.4 GW Solar+Battery project in California with status active.

2

The reported queue phase is C14; proposed COD is 2027-07-19.

3

Latest linked story: “California Approves 4,600 MWh Darden Battery Energy Storage Project” (Mercomindia.com, 2025-06-18).

Market and operating context

Queue date
2021-04-15
Proposed COD
2027-07-19
IA status
IA Executed
Study phase
C14
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

DARDEN — verified asset snapshot

FieldValue
Queue IDCAISO-1949
LocationFresno, California
TechnologySolar+Battery
Market / regionCAISO
Point of interconnectionManning-Midway 500kV Line
Queue date2021-04-15
Proposed COD2027-07-19
IA statusIA Executed