Briefing/projectactive
CPS Energy AvR1CT2 Rotor Replacement is a 23 MW Gas project in Texas, currently active.
CPS Energy is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2026-03-28.
- Queue ID
- ERCOT-25INR0531
- Location
- Bexar, Texas
- Technology
- Gas
- Developer
- CPS Energy
- Market / region
- ERCOT
- Point of interconnection
- 5475 Braunig 345kV
What stands out
1
CPS Energy AvR1CT2 Rotor Replacement is a 23 MW Gas project in Texas with status active.
2
CPS Energy is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2026-03-28.
Market and operating context
- Queue date
- 2023-10-13
- Proposed COD
- 2026-03-28
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.