Briefing on CORBY 2

Entity Briefing
Generated Oct 11, 2026·Dataset freshness not reported
476 MW
Proposed capacity
active
Current status
Battery
Technology
CAISO
Market / region
2031-03-16
Proposed COD
C14
Queue phase
Briefing/projectactive

CORBY 2 is a 476 MW Battery project in California, currently active.

The reported queue phase is C14. Proposed COD is 2031-03-16.

Queue ID
CAISO-1854
Location
Solano, California
Technology
Battery
Market / region
CAISO
Point of interconnection
Vaca-Dixon 230 kV

What stands out

1

CORBY 2 is a 476 MW Battery project in California with status active.

2

The reported queue phase is C14; proposed COD is 2031-03-16.

Market and operating context

Queue date
2021-04-15
Proposed COD
2031-03-16
IA status
System Impact Study
Study phase
C14
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

CORBY 2 — verified asset snapshot

FieldValue
Queue IDCAISO-1854
LocationSolano, California
TechnologyBattery
Market / regionCAISO
Point of interconnectionVaca-Dixon 230 kV
Queue date2021-04-15
Proposed COD2031-03-16
IA statusSystem Impact Study