Briefing/projectactive
Cherry Blossom Solar is a 150 MW Solar+Battery project in Georgia, currently active.
The reported queue phase is Facility Study. Proposed COD is 2023-06-15.
- Queue ID
- GTC-GI-142
- Location
- Twiggs, Georgia
- Technology
- Solar+Battery
- Market / region
- Southeast
- Point of interconnection
- Danville 115 kV Substation
What stands out
1
Cherry Blossom Solar is a 150 MW Solar+Battery project in Georgia with status active.
2
The reported queue phase is Facility Study; proposed COD is 2023-06-15.
Market and operating context
- Queue date
- 2020-08-13
- Proposed COD
- 2023-06-15
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.