Cherry Blossom Solar
150 MW hybrid in Twiggs, GA · In queue since August 2020 · Proposed COD June 2023
150 MW
Capacity
1
Components
Solar
5y 11m
In Queue
Facility Study
IA Phase
COD target: 2023
Total Duration
2y 10m
Schedule
37 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-06-15
Proposed commercial operation date per LBNL queue filing
Cherry Blossom Solar is a proposed 150 MW hybrid solar and battery energy storage project located in Twiggs County, Georgia. The project is listed in the Georgia Transmission (GTC) interconnection queue as queue ID GTC-GI-142, with an entry date of August 13, 2020. The proposed commercial operation date is June 15, 2023, and the project's interconnection agreement status is currently in the Facility Study phase.
The development project consists of 150 MW of solar photovoltaic generation. Cherry Blossom Solar has been mentioned in recent news coverage related to development activities.
Generated from interconnection queue and public data sources
Realization history for this asset — final cost vs plan, COD slip vs original date, and construction duration vs cohort. Retrospective context for the operating risk view above. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Twiggs
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Danville 115 kV Substation
Data Source
LBNL
Composite operating risk view for this asset — climate hazards across its remaining operating life, observed generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — 10-year P50 trajectory accounting for degradation, observed curtailment, and market conditions, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this asset — 10-year cashflow projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Cherry Blossom SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.