Briefing/projectactive
Camino Ranch Solar SLF is a 296 MW Solar+Battery project in Texas, currently active.
Camino Ranch Solar Project LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-12-09.
- Queue ID
- ERCOT-24INR0412
- Location
- Houston, Texas
- Technology
- Solar+Battery
- Developer
- Camino Ranch Solar Project LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap to Jim English (#3351) – Flat Branch (#3345) 138kV
What stands out
1
Camino Ranch Solar SLF is a 296 MW Solar+Battery project in Texas with status active.
2
Camino Ranch Solar Project LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2028-12-09.
Market and operating context
- Queue date
- 2022-10-06
- Proposed COD
- 2028-12-09
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.