Caliche Mound Solar is a 407 MW Solar project in Texas, currently active.
Tierra Blanco Solar LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-10-26.
- Queue ID
- ERCOT-23INR0056
- Location
- Deaf Smith, Texas
- Technology
- Solar
- Developer
- Tierra Blanco Solar LLC
- Market / region
- ERCOT
- Point of interconnection
- tap 345kV 23906 AJSwope - 23910 Windmill
What stands out
Caliche Mound Solar is a 407 MW Solar project in Texas with status active.
Tierra Blanco Solar LLC is the reported developer.
The reported queue phase is IA Executed; proposed COD is 2027-10-26.
Latest linked story: “Deaf Smith County Commission clears way for hydrogen plant, wind farm, solar farm” (KVII, 2024-02-13).
Market and operating context
- Queue date
- 2020-07-24
- Proposed COD
- 2027-10-26
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.