Briefing/projectactive
Bullring Wind 2 is a 304 MW Wind project in Texas, currently active.
Halcon Wind, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2028-06-30.
- Queue ID
- ERCOT-28INR0038
- Location
- Starr, Texas
- Technology
- Wind
- Developer
- Halcon Wind, LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 345 kV 80355 DelSol7A - 80079 Cruce Ckt 1
What stands out
1
Bullring Wind 2 is a 304 MW Wind project in Texas with status active.
2
Halcon Wind, LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2028-06-30.
Market and operating context
- Queue date
- 2024-05-09
- Proposed COD
- 2028-06-30
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.