Bullring Wind 2 (ERCOT-28INR0038) — Project Summary

Queue ID
ERCOT-28INR0038
Capacity
303.8 MW
Technology
Wind
Status
active
Location
Starr, TX
Region
ERCOT
Developer
Halcon Wind, LLC
IA Status
IA Executed

Bullring Wind 2

ERCOT-28INR0038BetaActiveWindERCOTLBNL + Live

303.8 MW generation in Starr, TX · In queue since May 2024 · Proposed COD June 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

303.8 MW

Capacity

1

Components

Wind

2y 6m

In Queue

IA Executed

IA Phase

Signed Nov 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 6m

IA → COD

2y 7m

Total Duration

1y 6m

Construction75%
Queue EntryMay 9, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementNov 3, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2028-06-30

Queue history
28INR0038 · 29 monthly ERCOT reports, May 2024 – Sep 2026

Projected COD moved

0 times

Jun 2028 → Jun 2028

Net change

0 months

first report to latest

Capacity

306 → 304 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMay 9, 2024
Interconnection agreement signedNov 3, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Jun 30, 2028
From queue filing
Developer in saved assessment
Halcon Wind, LLC
From queue filing
Status at research time
IA Executed
Active in ERCOT queue; standard generation interconnection agreement with AEP Texas filed at the Texas PUC in Nov 2025 (Bullring Wind 1-3 projects); ERCOT queue site lists FIS pending
Financing
Not recorded

Milestones in this assessment

IA executedNov 3, 2025

ERCOT standard generation interconnection agreement with AEP Texas filed at the PUC on 11/4/2025 (LBNL IA date 2025-11-03), covering Bullring Wind 1, 2 and 3.

interchange.puc.texas.gov
COD targetJun 30, 2028Latest in this assessment

Queue-derived COD target of mid-2028 for the Halcon Wind projects in Starr County; this is a queue figure, not a developer announcement.

quicksandcheck.com
Research sources and reasoning (6 recorded sources)

medium confidence at research time

  1. cleanview.co/power-projects/planned/wind-farms/texas/28INR0038/bullring-wind-2
  2. ercotqueue.com/project/28INR0038
  3. ercotqueue.com/developer/halcon-wind-llc
  4. interchange.puc.texas.gov/search/filings/?UtilityType=A&ControlNumber=35077&ItemMatch=Equal&DocumentType=ALL&SortBy=FileStamp&SortOrder=Descending
  5. ercot.com/files/docs/2026/05/01/MORA_July2026.pdf
  6. quicksandcheck.com/texas/starr-county/

Commercial operation date: No post-LBNL source gives a different date. LBNL proposed COD is 2028-06-30. Cleanview says 'Expected online 2028' and the ERCOT MORA July 2026 report lists the project with a 2028 year, both consistent with LBNL but not independent developer targets.

Developer: Every source (LBNL, ercotqueue.com, Texas PUC filings) names Halcon Wind, LLC. No parent or operating company was identified in the search results.

Status: LBNL shows IA Executed with an IA date of 2025-11-03. This matches the PUC Interchange filing of an ERCOT standard generation interconnection agreement dated 11/4/2025. No sign of construction start or withdrawal.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Bullring Wind 2 project is a proposed wind generation facility with a total capacity of 303.8 MW. It is located in Starr County, Texas, and is being developed by ACE DevCo NC LLC. The project is currently active in the ERCOT interconnection queue under queue ID ERCOT-28INR0038, with an interconnection queue entry date of May 9, 2024. The proposed commercial operation date is June 30, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.

The point of interconnection for the project is the Tap 345 kV 80355 DelSol7A - 80079 Cruce Ckt 1. The development has appeared in recent news coverage regarding renewable energy projects in Texas.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Starr

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Halcon Wind, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345 kV 80355 DelSol7A - 80079 Cruce Ckt 1

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.