Briefing/projectactive
Bug Tussle Wind Project is a 397 MW Wind project in Texas, currently active.
Bug Tussle Wind, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2028-09-18.
- Queue ID
- ERCOT-23INR0441
- Location
- Lamar, Texas
- Technology
- Wind
- Developer
- Bug Tussle Wind, LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 1729 Valley South and 1692 Paris
What stands out
1
Bug Tussle Wind Project is a 397 MW Wind project in Texas with status active.
2
Bug Tussle Wind, LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2028-09-18.
Market and operating context
- Queue date
- 2022-01-13
- Proposed COD
- 2028-09-18
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.