Bug Tussle Wind Project (ERCOT-23INR0441) — Project Summary

Queue ID
ERCOT-23INR0441
Capacity
396.8 MW
Technology
Wind
Status
active
Location
Lamar, TX
Region
ERCOT
Developer
Bug Tussle Wind, LLC
IA Status
IA Executed

Bug Tussle Wind Project

ERCOT-23INR0441BetaActiveWindERCOTLBNL + Live

396.8 MW generation in Lamar, TX · In queue since January 2022 · Proposed COD September 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

396.8 MW

Capacity

1

Components

Wind

4y 10m

In Queue

IA Executed

IA Phase

Signed Jul 2024

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 6m

IA → COD

4y 2m

Total Duration

2y 6m

Construction75%
Queue EntryJan 13, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJul 10, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2028-09-18

Queue history
23INR0441 · 50 monthly ERCOT reports, Aug 2022 – Sep 2026

Projected COD moved

5 times

Sep 2024 → Sep 2028

Net change

+48 months

first report to latest

Capacity

312 → 397 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJan 13, 2022
Facilities study approvedJan 18, 2024
Interconnection agreement signedJul 10, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Sep 18, 2028
From queue filing
Developer in saved assessment
Cielo Wind Power
Filed as Bug Tussle Wind, LLC
Status at research time
Active
Active, IA executed 2024-07-10. Still in development, with construction targeted for 2026 and a landowner nuisance lawsuit pending as of mid-2024.
Financing
Not recorded
Research sources and reasoning (6 recorded sources)

medium confidence at research time

  1. cielowind.com/project/bug-tussle-wind-ranch/
  2. cielowind.com/wp-content/uploads/2024/02/Bug-Tussle-Wind-Ranch-Fact-Sheet-Feb-5th-2024-Rudux2.pdf
  3. texasscorecard.com/local/tussle-over-east-texas-wind-farm-headed-to-trial/
  4. eextra.news/paris/2024/06/02/wind-ranch-coming-to-bug-tussle-300-million-investment/
  5. cleanview.co/power-projects/planned/wind-farms/texas/23INR0441/bug-tussle-wind-project-
  6. ercotqueue.com/project/23INR0441

Commercial operation date: Cielo Wind's project page says 'Construction is targeted to start in 2026 and hopes to be completed by 2029', which is consistent with LBNL's 2028-09-18 COD. Cleanview also shows 'Expected online 2028'. The 2024 article's 2026 completion target is outdated, so LBNL's date is kept.

Developer: The Cielo Wind fact sheet describes the project as 'a wind project development of Bug Tussle Wind, LLC', and Texas Scorecard names Cielo Wind as the developer. The LBNL filing entity is the project LLC and Cielo is the operating developer.

Status: LBNL shows the project as active with an executed IA. Cielo Wind lists it as 'Project in development' with construction targeted for 2026. The ERCOT queue trackers also show it as active.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Bug Tussle Wind Project is a proposed 396.8 MW wind generation project located in Lamar County, Texas. The developer is Bug Tussle Wind, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-23INR0441, with a queue entry date of January 13, 2022, and a proposed commercial operation date of September 18, 2028.

The project's interconnection agreement has been executed as of July 10, 2024. The point of interconnection is Tap 1729 Valley South and 1692 Paris. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Lamar

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Bug Tussle Wind, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 1729 Valley South and 1692 Paris

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.