Query
BRP Pyxis BESS
Type
Entity Briefing
Entity
BRP Pyxis BESS
State
TN
Technology
battery
Generated
2026-10-20T01:20:12.697Z

Briefing on BRP Pyxis BESS

Entity Briefing
Generated Oct 20, 2026·Dataset freshness not reported
207 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2028-12-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

BRP Pyxis BESS is a 207 MW Battery project in Texas, currently active.

BRP Pyxis BESS LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-12-01.

Queue ID
ERCOT-23INR0094
Location
Ward, Texas
Technology
Battery
Developer
BRP Pyxis BESS LLC
Market / region
ERCOT
Point of interconnection
tap 138kV 1009 Yucca - 11197 Sand Tank Pod

What stands out

1

BRP Pyxis BESS is a 207 MW Battery project in Texas with status active.

2

BRP Pyxis BESS LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-12-01.

Market and operating context

Queue date
2020-09-25
Proposed COD
2028-12-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

BRP Pyxis BESS — verified asset snapshot

FieldValue
Queue IDERCOT-23INR0094
LocationWard, Texas
TechnologyBattery
DeveloperBRP Pyxis BESS LLC
Market / regionERCOT
Point of interconnectiontap 138kV 1009 Yucca - 11197 Sand Tank Pod
Queue date2020-09-25
Proposed COD2028-12-01