BRP Pyxis BESS is a 207 MW Battery project in Texas, currently active.
BRP Pyxis BESS LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-12-01.
- Queue ID
- ERCOT-23INR0094
- Location
- Ward, Texas
- Technology
- Battery
- Developer
- BRP Pyxis BESS LLC
- Market / region
- ERCOT
- Point of interconnection
- tap 138kV 1009 Yucca - 11197 Sand Tank Pod
What stands out
1
BRP Pyxis BESS is a 207 MW Battery project in Texas with status active.
2
BRP Pyxis BESS LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2028-12-01.
Market and operating context
- Queue date
- 2020-09-25
- Proposed COD
- 2028-12-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.