Blue Spring Solar is a 301 MW Solar project in Texas, currently active.
Flat Creek Solar, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-10-28.
- Queue ID
- ERCOT-28INR0433
- Location
- Haskell, Texas
- Technology
- Solar
- Developer
- Flat Creek Solar, LLC
- Market / region
- ERCOT
- Point of interconnection
- #60515 Clear Crossing 345 kV
What stands out
Blue Spring Solar is a 301 MW Solar project in Texas with status active.
Flat Creek Solar, LLC is the reported developer.
The reported queue phase is Facility Study; proposed COD is 2028-10-28.
Latest linked story: “Solar project updates: EDP Renewables, Engie, Exus Renewables and more” (pv magazine USA, 2025-07-23).
Market and operating context
- Queue date
- 2025-10-03
- Proposed COD
- 2028-10-28
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.