Briefing/projectactive
Hollow Branch Creek Storage is a 460 MW Solar+Battery project in Texas, currently active.
Hollow Branch Creek Solar LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-12-31.
- Queue ID
- ERCOT-24INR0423
- Location
- Leon, Texas
- Technology
- Solar+Battery
- Developer
- Hollow Branch Creek Solar LLC
- Market / region
- ERCOT
- Point of interconnection
- Jewett – Singleton 345 kV [PTI Bus # 3390 – 44645]
What stands out
1
Hollow Branch Creek Storage is a 460 MW Solar+Battery project in Texas with status active.
2
Hollow Branch Creek Solar LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2027-12-31.
Market and operating context
- Queue date
- 2022-09-02
- Proposed COD
- 2027-12-31
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.