Briefing/projectactive
Betel Storage II is a 500 MW Battery project in Texas, currently active.
BETEL STORAGE II is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2026-12-17.
- Queue ID
- ERCOT-26INR0633
- Location
- Milam, Texas
- Technology
- Battery
- Developer
- BETEL STORAGE II
- Market / region
- ERCOT
- Point of interconnection
- 3377 Little Pond 345
What stands out
1
Betel Storage II is a 500 MW Battery project in Texas with status active.
2
BETEL STORAGE II is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2026-12-17.
Market and operating context
- Queue date
- 2025-01-28
- Proposed COD
- 2026-12-17
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.