Prairie Ridge (Gas - CC) is a 1.7 GW Gas project in Texas, currently active.
Tenaska Power Generation, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2032-06-01.
- Queue ID
- ERCOT-30INR0071
- Location
- Franklin, Texas
- Technology
- Gas
- Developer
- Tenaska Power Generation, LLC
- Market / region
- ERCOT
- Point of interconnection
- TAP 345 KV 11699 WOODARD - 11702 BEARPEN
What stands out
1
Prairie Ridge (Gas - CC) is a 1.7 GW Gas project in Texas with status active.
2
Tenaska Power Generation, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2032-06-01.
Market and operating context
- Queue date
- 2025-12-01
- Proposed COD
- 2032-06-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.