Axtell BESS
Type
Entity Briefing
Entity
Axtell BESS
State
TN
Technology
battery
Generated
2026-10-19T18:04:55.812Z

Briefing on Axtell BESS

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
307 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2029-04-16
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Axtell BESS is a 307 MW Battery project in Texas, currently active.

Axtell BESS LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-04-16.

Queue ID
ERCOT-28INR0157
Location
Mclennan, Texas
Technology
Battery
Developer
Axtell BESS LLC
Market / region
ERCOT
Point of interconnection
#13401 Tiger Creek Switch 345kV

What stands out

1

Axtell BESS is a 307 MW Battery project in Texas with status active.

2

Axtell BESS LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2029-04-16.

Market and operating context

Queue date
2024-10-01
Proposed COD
2029-04-16
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Axtell BESS — verified asset snapshot

FieldValue
Queue IDERCOT-28INR0157
LocationMclennan, Texas
TechnologyBattery
DeveloperAxtell BESS LLC
Market / regionERCOT
Point of interconnection#13401 Tiger Creek Switch 345kV
Queue date2024-10-01
Proposed COD2029-04-16