Axtell BESS (ERCOT-28INR0157) — Project Summary

Queue ID
ERCOT-28INR0157
Capacity
306.94 MW
Technology
Battery
Status
active
Location
Mclennan, TX
Region
ERCOT
Developer
Axtell BESS LLC
IA Status
Facility Study

Axtell BESS

ERCOT-28INR0157BetaActiveBatteryERCOTLBNL + Live

306.94 MW storage in Mclennan, TX · In queue since October 2024 · Proposed COD April 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

306.94 MW

Capacity

1

Components

Battery

2y 1m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 6m

Facilities Study50%
Queue EntryOct 1, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-04-16

Queue history
28INR0157 · 17 monthly ERCOT reports, Apr 2025 – Sep 2026

Projected COD moved

1 time

Jan 2028 → Apr 2029

Net change

+15 months

first report to latest

Capacity

307 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedOct 1, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Apr 16, 2029
From queue filing
Developer in saved assessment
Perfect Power (acquired by FIC Partners Management)
Ownership change in saved research
Status at research time
Active
Active in the ERCOT queue (Facility Study, no IA executed). 300 MW/680 MWh BESS near Waco, TX, in early-stage development under Perfect Power, now owned by FIC.
Financing
Not recorded
Ownership history
  1. 2026-08·Perfect Power (PP Axtell BESS LLC)→FIC Partners Management (parent of Perfect Power)enerdatics.com

Milestones in this assessment

Ownership changeAug 2026Latest in this assessment

FIC Partners Management acquired Perfect Power, whose pipeline includes the early-stage Axtell BESS.

enerdatics.com
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. enerdatics.com/insights/why-fics-perfect-power-deal-buys-contracted-ercot-cash-flow-and-850-mw-of-optionality
  2. pv-tech.org/fic-acquires-us-solar-plus-storage-firm-perfect-power/
  3. perfectpowerllc.com/proj/under_dev.html
  4. fieldprospects.com/developers/pp-axtell-bess-llc/
  5. interconnection.fyi/project/ercot-28inr0157

Commercial operation date: Only the LBNL/ERCOT queue date (proposed COD 2029-04-16, mirrored by interconnection.fyi) gives a date. The Perfect Power project page says the project is 'in the early stages of development', but the snippet cuts off before any target date.

Developer: The project entity is PP Axtell BESS LLC, a Perfect Power subsidiary, and the Perfect Power site lists Axtell BESS as a project under development. FIC Partners Management recently acquired Perfect Power, and Enerdatics' coverage of the deal counts Axtell BESS as early-stage development capacity in the acquired pipeline.

Status: The LBNL status of active is consistent with the Perfect Power project page and the Enerdatics description of Axtell BESS as early stage. No source reports a permit, financing or construction start.

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Axtell BESS is a proposed battery energy storage development project located in McLennan County, Texas. Axtell BESS LLC is developing the project, which has a total planned capacity of 306.94 MW. The project consists of a single battery storage component. It is designed to connect to the grid at the Tiger Creek Switch 345 kV substation (#13401).

The project is listed in the Electric Reliability Council of Texas (ERCOT) interconnection queue under the identifier 28INR0157. It entered the queue on October 1, 2024, and its status is currently active. The project is in the Facility Study phase of the interconnection process, and its proposed commercial operation date is April 16, 2029.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Mclennan

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Axtell BESS LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

#13401 Tiger Creek Switch 345kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.