Briefing/projectactive
Aurelius Solar is a 1.1 GW Solar project in Texas, currently active.
IP Roman, is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2028-06-30.
- Queue ID
- ERCOT-29INR0003
- Location
- Deaf Smith, Texas
- Technology
- Solar
- Developer
- IP Roman,
- Market / region
- ERCOT
- Point of interconnection
- 23908 Deaf Smith station 345 kV
What stands out
1
Aurelius Solar is a 1.1 GW Solar project in Texas with status active.
2
IP Roman, is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2028-06-30.
4
Latest linked story: “Intersect Power's $1 billion project ignites tax debate in Gray County Commission Court” (KVII, 2024-01-15).
Market and operating context
- Queue date
- 2023-07-18
- Proposed COD
- 2028-06-30
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.