Briefing on ATHOS POWER PLANT

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
908 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
CAISO
Market / region
2027-05-17
Proposed COD
C10
Queue phase
Briefing/projectactive

ATHOS POWER PLANT is a 908 MW Solar+Battery project in California, currently active.

The reported queue phase is C10. Proposed COD is 2027-05-17.

Queue ID
CAISO-1405
Location
Riverside, California
Technology
Solar+Battery
Market / region
CAISO
Point of interconnection
Red Bluff Substation 230kV

What stands out

1

ATHOS POWER PLANT is a 908 MW Solar+Battery project in California with status active.

2

The reported queue phase is C10; proposed COD is 2027-05-17.

3

Latest linked story: “Tesla lands 15.3 GWh Megapack supply contract” (pv magazine USA, 2024-07-19).

Market and operating context

Queue date
2017-05-01
Proposed COD
2027-05-17
IA status
IA Executed
Study phase
C10
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

ATHOS POWER PLANT — verified asset snapshot

FieldValue
Queue IDCAISO-1405
LocationRiverside, California
TechnologySolar+Battery
Market / regionCAISO
Point of interconnectionRed Bluff Substation 230kV
Queue date2017-05-01
Proposed COD2027-05-17
IA statusIA Executed