Briefing on ARIDA 2 SOLAR FARM

Entity Briefing
Generated Oct 11, 2026·Dataset freshness not reported
1.4 GW
Proposed capacity
active
Current status
Solar+Battery
Technology
CAISO
Market / region
2029-05-31
Proposed COD
C12
Queue phase
Briefing/projectactive

ARIDA 2 SOLAR FARM is a 1.4 GW Solar+Battery project in Nevada, currently active.

The reported queue phase is C12. Proposed COD is 2029-05-31.

Queue ID
CAISO-1647
Location
Clark, Nevada
Technology
Solar+Battery
Market / region
CAISO
Point of interconnection
Mohave Substation 500kV

What stands out

1

ARIDA 2 SOLAR FARM is a 1.4 GW Solar+Battery project in Nevada with status active.

2

The reported queue phase is C12; proposed COD is 2029-05-31.

Market and operating context

Queue date
2019-04-15
Proposed COD
2029-05-31
IA status
In Progress (unknown study)
Study phase
C12
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

ARIDA 2 SOLAR FARM — verified asset snapshot

FieldValue
Queue IDCAISO-1647
LocationClark, Nevada
TechnologySolar+Battery
Market / regionCAISO
Point of interconnectionMohave Substation 500kV
Queue date2019-04-15
Proposed COD2029-05-31
IA statusIn Progress (unknown study)