Query
Appaloosa Run BESS
Type
Entity Briefing
Entity
Appaloosa Run BESS
State
TN
Technology
battery
Generated
2026-10-19T08:13:18.684Z

Briefing on Appaloosa Run BESS

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
103 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2026-08-30
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Appaloosa Run BESS is a 103 MW Battery project in Texas, currently active.

APPALOOSA RUN STORAGE, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2026-08-30.

Queue ID
ERCOT-24INR0238
Location
Upton, Texas
Technology
Battery
Developer
APPALOOSA RUN STORAGE, LLC
Market / region
ERCOT
Point of interconnection
New Palouse 138kV (#60278)

What stands out

1

Appaloosa Run BESS is a 103 MW Battery project in Texas with status active.

2

APPALOOSA RUN STORAGE, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2026-08-30.

4

Latest linked story: “NextEra Energy picks up DuPont PPA” (reNEWS.BIZ, 2023-04-21).

Market and operating context

Queue date
2022-03-07
Proposed COD
2026-08-30
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Appaloosa Run BESS — verified asset snapshot

FieldValue
Queue IDERCOT-24INR0238
LocationUpton, Texas
TechnologyBattery
DeveloperAPPALOOSA RUN STORAGE, LLC
Market / regionERCOT
Point of interconnectionNew Palouse 138kV (#60278)
Queue date2022-03-07
Proposed COD2026-08-30