Query
Amite Energy Storage II
Type
Entity Briefing
Entity
Amite Energy Storage II
Technology
battery
Generated
2026-10-05T07:14:47.470Z

Briefing on Amite Energy Storage II

Entity Briefing
Generated Oct 5, 2026·Dataset freshness not reported
208 MW
Proposed capacity
active
Current status
Battery
Technology
MISO
Market / region
2028-02-25
Proposed COD
ERAS Study Cycle 2
Queue phase
Briefing/projectactive

Amite Energy Storage II is a 208 MW Battery project in Louisiana, currently active.

NextEra Energy Resources Development, LLC is the reported developer. The reported queue phase is ERAS Study Cycle 2. Proposed COD is 2028-02-25.

Queue ID
MISO-E0024
Location
Tangipahoa Parish, Louisiana
Technology
Battery
Developer
NextEra Energy Resources Development, LLC
Market / region
MISO
Point of interconnection
Amite 115kV Substation

What stands out

1

Amite Energy Storage II is a 208 MW Battery project in Louisiana with status active.

2

NextEra Energy Resources Development, LLC is the reported developer.

3

The reported queue phase is ERAS Study Cycle 2; proposed COD is 2028-02-25.

Market and operating context

Queue date
2025-08-06
Proposed COD
2028-02-25
IA status
In Progress (unknown study)
Study phase
ERAS Study Cycle 2
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Amite Energy Storage II — verified asset snapshot

FieldValue
Queue IDMISO-E0024
LocationTangipahoa Parish, Louisiana
TechnologyBattery
DeveloperNextEra Energy Resources Development, LLC
Market / regionMISO
Point of interconnectionAmite 115kV Substation
Queue date2025-08-06
Proposed COD2028-02-25