Briefing on Altamaha Green Energy

Entity Briefing
Generated Oct 10, 2026·Dataset freshness not reported
70 MW
Proposed capacity
active
Current status
Other
Technology
Southeast
Market / region
2028-03-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Altamaha Green Energy is a 70 MW Other project in Georgia, currently active.

The reported queue phase is Facility Study. Proposed COD is 2028-03-01.

Queue ID
GTC-GI-195
Location
Wayne, Georgia
Technology
Other
Market / region
Southeast
Point of interconnection
Jessup – Ludowici Primary 115 kV TL

What stands out

1

Altamaha Green Energy is a 70 MW Other project in Georgia with status active.

2

The reported queue phase is Facility Study; proposed COD is 2028-03-01.

3

Latest linked story: “Wood burning plant almost went unnoticed in Georgia county with high asthma rates” (Columbus Ledger-Enquirer, 2025-06-12).

Market and operating context

Queue date
2024-08-20
Proposed COD
2028-03-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Altamaha Green Energy — verified asset snapshot

FieldValue
Queue IDGTC-GI-195
LocationWayne, Georgia
TechnologyOther
Market / regionSoutheast
Point of interconnectionJessup – Ludowici Primary 115 kV TL
Queue date2024-08-20
Proposed COD2028-03-01
IA statusFacility Study