Briefing on Alkali Creek Wind

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
474 MW
Proposed capacity
active
Current status
Wind
Technology
ERCOT
Market / region
2028-12-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Alkali Creek Wind is a 474 MW Wind project in Texas, currently active.

Alkali Creek Wind, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-12-01.

Queue ID
ERCOT-28INR0415
Location
Fisher, Texas
Technology
Wind
Developer
Alkali Creek Wind, LLC
Market / region
ERCOT
Point of interconnection
Tap 345 kV BUS #1048 Tonkawa - BUS #11050 Dusty Road

What stands out

1

Alkali Creek Wind is a 474 MW Wind project in Texas with status active.

2

Alkali Creek Wind, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-12-01.

Market and operating context

Queue date
2025-08-18
Proposed COD
2028-12-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Alkali Creek Wind — verified asset snapshot

FieldValue
Queue IDERCOT-28INR0415
LocationFisher, Texas
TechnologyWind
DeveloperAlkali Creek Wind, LLC
Market / regionERCOT
Point of interconnectionTap 345 kV BUS #1048 Tonkawa - BUS #11050 Dusty Road
Queue date2025-08-18
Proposed COD2028-12-01